Works at the northern intersection are progressing on time and on budget.
The first primer seal was laid on Friday 29 March in preparation for the final seal of asphalt from 8 to 12 April 2019.
New kerbing works will be carried from 1 to 5 April 2019.
Traffic will start using the new intersection layout on Thursday 4 April 2019 under reduced speeds on the primer seal surface.
Traffic control measures will be in place.